Days 16 - 17
We are finishing the main entrance and had another BBQ and Pool party at the end of the day to celebrate a big milestone. We are ahead of schedule and the work is high quality.
Days 18 - 25
The bases on the lunch area used to be manu...thats a great wood but since it was such a tall structure from ground level they had been joined some 4 times and some were even rotten... when we took the floor out they were very loose and so we made 8 concrete pillars, each 150 cm buried deep into the ground and from there we will have single (no joints) pine posts. Instead of a pin we are using a metal tube that will hold the post in place.
And finally the Mirador had to come down...
More photos from this project will be posted on our Facebook page this week!